Initial review · graded Oct 20, 2026 · Headline, summary and grade are analysis of the bill text, not a finding about any person · How we grade
Caption
relating to the authority of the Public Utility Commission of Texas
to ensure the independent organization certified for the ERCOT
power region has adequate reserve power to prevent blackout
conditions.
Last in line after every other source. Who pays? The rules decide.
The bill orders the Public Utility Commission to write rules for buying emergency backup power generation capacity, on top of existing reliability services, to prevent blackouts from power shortages in the ERCOT region. It requires ERCOT to contract for a set amount of that reserve capacity and to use every other power source and demand reduction before calling on it. The rules must set how much reserve is needed and how the costs of keeping and using that reserve are shared.
Labels
Labels: ZOMBIE BILL. Died 2 times: 88R HB 3178 (Died in committee) and this bill (Died in committee). Checked against 88R only.DO-OVER. Reworked text of a bill filed before that died: 88R HB 3178 (Died in committee). Filed in 2 sessions, counting this one. Checked against 88R only.TRY NO. 2. Filed in 2 sessions: 88R and 89R. Checked against 88R only.NEVER GOT A HEARING. Filed Dec 12, 2024 and referred to the House State Affairs committee. No public hearing. The bill died.
relating to the authority of the Public Utility Commission of Texas
to ensure the independent organization certified for the ERCOT
power region has adequate reserve power to prevent blackout
conditions.
WHAT IT DOES
Last in line after every other source. Who pays? The rules decide.
The bill orders the Public Utility Commission to write rules for buying emergency backup power generation capacity, on top of existing reliability services, to prevent blackouts from power shortages in the ERCOT region. It requires ERCOT to contract for a set amount of that reserve capacity and to use every other power source and demand reduction before calling on it. The rules must set how much reserve is needed and how the costs of keeping and using that reserve are shared.
“mechanisms for equitably sharing the costs of
making the reserve capacity available and the costs of generated
power provided to prevent blackout conditions”
Last action, Mar 15, 2023: Referred to State Affairs
Relating to the authority of the Public Utility Commission of Texas to ensure the independent organization certified for the ERCOT power region has adequate reserve power to prevent blackout conditions.
Caption, 88R bill history
Sources
Texas House · Filed Dec 12, 2024
03/12/2025 H Referred to State Affairs: Mar 12 2025 11:15AM
Data snapshot Oct 26, 2026 at 4:19 AM CDT. Grades, charges, quotes and corrections follow the published record.
House committee · State Affairs · Final status: Died in committee
Subjects
Disaster Preparedness & Relief
Utilities--Electric
ELECTRIC RELIABILITY COUNCIL OF TEXAS (ERCOT)
PUBLIC UTILITY COMMISSION
Text
The text as introduced · 310 words
89R3502 ANG-F
By: Rosenthal
H.B. No. 1603
A BILL TO BE ENTITLED
AN ACT
relating to the authority of the Public Utility Commission of Texas
to ensure the independent organization certified for the ERCOT
power region has adequate reserve power to prevent blackout
conditions.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1. Section 39.159, Utilities Code, is amended by
adding Subsections (f) and (g) to read as follows:
(f) The commission by rule shall develop a process for
procuring emergency reserve power generation capacity, in addition
to ancillary and reliability services procured under Subsections
(b) and (d), as necessary to prevent blackout conditions caused by
shortages of generated power in the ERCOT power region. The rules
must provide:
(1) parameters for estimating the amount of emergency
reserve power generation capacity necessary to prevent blackout
conditions; and
(2) mechanisms for equitably sharing the costs of
making the reserve capacity available and the costs of generated
power provided to prevent blackout conditions.
(g) In accordance with rules adopted under Subsection (f),
the independent organization certified under Section 39.151 for the
ERCOT power region shall adopt procedures and enter contracts as
necessary to ensure the availability of a defined amount of
emergency reserve power generation capacity the organization may
call on to prevent blackouts caused by shortages of generated
power. Before the independent organization calls on the emergency
reserve power generation capacity to prevent blackout conditions,
the organization shall use all other sources of power and demand
reduction available in accordance with commission rules adopted
under this section.
SECTION 2. This Act takes effect immediately if it receives
a vote of two-thirds of all the members elected to each house, as
provided by Section 39, Article III, Texas Constitution. If this
Act does not receive the vote necessary for immediate effect, this
Act takes effect September 1, 2025.