Monitoring the Session

SB 2888

Cook Bill Ties Data Center Tax Breaks To Liquid Cooling

Died in committee

Verdict: No flags

No flagsInitial review
Sen. Molly CookDSenate 15

Initial review · graded Oct 20, 2026 · Headline, summary and grade are analysis of the bill text, not a finding about any person · How we grade

Caption

relating to the temporary sales and use tax exemptions for certain tangible personal property related to data centers and large data center projects.

Caption from analyzed text · version I.

Summary

Energy Star servers too, or no sales tax exemption. Starts September 1, 2026.

This bill adds energy-efficiency conditions that data centers must meet to qualify for the state's existing temporary sales and use tax breaks for data centers and large data center projects. It affects data center owners, operators and tenants who apply to the comptroller for certification. Starting with certifications on or after September 1, 2026, a project must use liquid cooling instead of air cooling, row- or rack-based air cooling instead of room-based air cooling, and Energy Star-certified servers, or it gets no exemption.

Labels

Labels: NEVER GOT A HEARING. Filed Mar 14, 2025 and referred to the Senate Finance committee. No public hearing. The bill died.

Receipt

The receipt

89R-SB2888 · 2025-03-14

SOLD BY

ITEM

relating to the temporary sales and use tax exemptions for certain tangible personal property related to data centers and large data center projects.

WHAT IT DOES

Energy Star servers too, or no sales tax exemption. Starts September 1, 2026.

This bill adds energy-efficiency conditions that data centers must meet to qualify for the state's existing temporary sales and use tax breaks for data centers and large data center projects. It affects data center owners, operators and tenants who apply to the comptroller for certification. Starting with certifications on or after September 1, 2026, a project must use liquid cooling instead of air cooling, row- or rack-based air cooling instead of room-based air cooling, and Energy Star-certified servers, or it gets no exemption.

CHARGES

[ ] NONE FOUND

TOTAL

No fiscal note in the loaded record.

HISTORY

  1. Received by the Secretary of the Senate
  2. Filed
  3. Read first time
  4. Referred to Finance
FILED UNDER

DATA CENTERS, WATER AND THE GRID

THE TEXT

“use of Energy Star-certified servers”

Bill text, introduced version (I)

The bill makes data centers meet cooling and server efficiency rules before they can get the state sales tax break.

No flags

THANK YOU FOR CHECKING THE RECEIPT

CAMPAIGN PAID FOR BY

CAMPAIGN PAID FOR BY

Donors

Texas Trial Lawyers Association PAC$15KGregory Stocks$10,000Amber Alonso$6,500

Not tied to this bill.

Sources

The author's campaign account only. Own money and internal transfers are separate on the member page.

Derived itemized flow · Oct 27, 2024 to Jun 30, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Texas Trial Lawyers Association PAC$15,000.00

Texas Trial Lawyers Association PAC

$15,000.00

Cash
$15,000.00
Paid by others
$0.00
Total
$15,000.00

Also funds 137 other sitting lawmakers.

Derived recipient stock · Jul 24, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Dec 13, 2024 to Jun 5, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 100987960, 101029944, 101057026.

Gregory Stocks$10,000.00
Amber Alonso$6,500.00
Money

Missing data does not establish zero giving. Display amounts are rounded.

×

Texas Trial Lawyers Association PAC

$15,000.00

Cash
$15,000.00
Paid by others
$0.00
Total
$15,000.00

Also funds 137 other sitting lawmakers.

Derived recipient stock · Jul 24, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Dec 13, 2024 to Jun 5, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 100987960, 101029944, 101057026.

Votes

No floor vote loaded for this bill.

Fiscal

No fiscal note in the loaded record.

How this was graded

Analysis of text version I by claude-opus-5-5, Oct 20, 2026, against the published rubric.

Sources

Texas Senate · Filed Mar 14, 2025

04/07/2025 S Referred to Finance

Texas Legislature Online · Introduced

Data snapshot Oct 26, 2026 at 4:20 AM CDT. Grades, charges, quotes and corrections follow the published record.

Senate committee · Finance · Final status: Died in committee

Subjects

Energy--Conservation

Property Interests--Personal Property

Taxation--General

Taxation--Sales

Text

The text as introduced · 749 words

89R15899 JBD-D

By: Cook
S.B. No. 2888

A BILL TO BE ENTITLED

AN ACT

relating to the temporary sales and use tax exemptions for certain

tangible personal property related to data centers and large data

center projects.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

SECTION 1. Section 151.359(d), Tax Code, is amended to read

as follows:

(d) Subject to Subsection (k), a data center may be

certified by the comptroller as a qualifying data center for

purposes of this section if, on or after September 1, 2013:

(1) a single qualifying occupant:

(A) contracts with a qualifying owner or

qualifying operator to lease space in which the qualifying occupant

will locate a data center; or

(B) occupies a space that was not previously used

as a data center in which the qualifying occupant will locate a data

center, in the case of a qualifying occupant who is also the

qualifying operator and the qualifying owner; [ and ]

(2) the qualifying owner, qualifying operator, or

qualifying occupant, jointly or independently:

(A) creates at least 20 qualifying jobs in the

county in which the data center is located, not including jobs moved

from one county in this state to another county in this state; and

(B) makes or agrees to make a capital investment,

on or after September 1, 2013, of at least $200 million in that

particular data center over a five-year period beginning on the

date the data center is certified by the comptroller as a qualifying

data center ; and

(3) the data center described by Subdivision (1)

includes the following energy conservation and efficiency

measures:

(A) use of a liquid cooling system instead of an

air cooling system;

(B) use of a row- or rack-based air cooling

system instead of a room-based air cooling system; and

(C) use of Energy Star-certified servers .

SECTION 2. Section 151.3595(d), Tax Code, is amended to

read as follows:

(d) Subject to Subsection (j), a large data center project

may be certified by the comptroller as a qualifying large data

center project for purposes of this section if, on or after June 1,

2015:

(1) a single qualifying occupant:

(A) contracts with a qualifying owner or

qualifying operator to lease space in which the qualifying occupant

will locate a large data center project; or

(B) occupies a space that was not previously used

as a data center in which the qualifying occupant will locate a

large data center project, in the case of a qualifying occupant who

is also the qualifying operator and the qualifying owner; [ and ]

(2) the qualifying owner, qualifying operator, or

qualifying occupant, independently or jointly:

(A) creates at least 40 qualifying jobs in the

county in which the large data center project is located, not

including jobs moved from one county in this state to another county

in this state;

(B) on or after May 1, 2015, makes or agrees to

make a capital investment of at least $500 million in that

particular large data center project, the amount of which may not

include a capital investment to replace personal property

previously placed in service in that large data center project,

over a five-year period beginning on the earlier of:

(i) the date the large data center project

submits the application described by Subsection (e); or

(ii) the date the large data center project

is certified by the comptroller as a qualifying large data center

project; and

(C) agrees to contract for at least 20 megawatts

of transmission capacity for operation of the large data center

project ; and

(3) the large data center project includes the

following energy conservation and efficiency measures:

(A) use of a liquid cooling system instead of an

air cooling system;

(B) use of a row- or rack-based air cooling

system instead of a room-based air cooling system; and

(C) use of Energy Star-certified servers .

SECTION 3. (a) Section 151.359(d), Tax Code, as amended by

this Act, applies only to the certification of a data center as a

qualifying data center for purposes of Section 151.359, Tax Code,

as amended by this Act, on or after September 1, 2026.

(b) Section 151.3595(d), Tax Code, as amended by this Act,

applies only to the certification of a large data center project as

a qualifying large data center project for purposes of Section

151.3595, Tax Code, as amended by this Act, on or after September 1,

2026.

SECTION 4. This Act takes effect September 1, 2025.