Caption
relating to a certificate of public convenience and necessity to construct an electric transmission line.
Caption from analyzed text · version I.
Summary
Only with every affected landowner’s written consent and the rights-of-way already bought.
The bill lets an electric utility build a longer transmission line without first amending its state certificate, raising the limit from three miles to five miles for lines that run to a substation or metering point serving customers. It touches electric utilities, the state utility commission, and landowners along short new lines. On the ground, more short lines can be built without a new commission certificate case, but only if every directly affected landowner gives written consent and all rights-of-way are already bought.
Receipt
The receipt
89R-SB2930 · 2025-03-14
SOLD BY
+ 1 coauthor
ITEM
relating to a certificate of public convenience and necessity to construct an electric transmission line.
WHAT IT DOES
Only with every affected landowner’s written consent and the rights-of-way already bought.
The bill lets an electric utility build a longer transmission line without first amending its state certificate, raising the limit from three miles to five miles for lines that run to a substation or metering point serving customers. It touches electric utilities, the state utility commission, and landowners along short new lines. On the ground, more short lines can be built without a new commission certificate case, but only if every directly affected landowner gives written consent and all rights-of-way are already bought.
CHARGES
[ ] NONE FOUND
TOTAL
No fiscal note in the loaded record.
HISTORY
- Received by the Secretary of the Senate
- Filed
- Read first time
- Referred to Business & Commerce
- Co-author authorized
FILED UNDER
DATA CENTERS, WATER AND THE GRID
The bill widens the set of grid transmission lines a utility can build to customer substations without a new state certificate review, from three to five miles.
THANK YOU FOR CHECKING THE RECEIPT
CAMPAIGN PAID FOR BY
CAMPAIGN PAID FOR BY
Donors
Not tied to this bill.
Sources
The author's campaign account only. Own money and internal transfers are separate on the member page.
Derived itemized flow · Jul 25, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Texans for Lawsuit Reform PAC$60,000.00
Texans for Lawsuit Reform PAC
$60,000.00
- Cash
- $60,000.00
- Paid by others
- $0.00
- Total
- $60,000.00
Also funds 124 other sitting lawmakers.
Derived recipient stock · Jul 10, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.
TEC account match.
TeamSources
Derived itemized flow · Oct 15, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 101012623, 101029380, 101072732.
Missing data does not establish zero giving. Display amounts are rounded.
Texans for Lawsuit Reform PAC
$60,000.00
- Cash
- $60,000.00
- Paid by others
- $0.00
- Total
- $60,000.00
Also funds 124 other sitting lawmakers.
Derived recipient stock · Jul 10, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.
TEC account match.
TeamSources
Derived itemized flow · Oct 15, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 101012623, 101029380, 101072732.
Votes
No floor vote loaded for this bill.
Fiscal
No fiscal note in the loaded record.
How this was graded
Analysis of text version I by claude-opus-5-5, Oct 20, 2026, against the published rubric.
Sources
Texas Senate · Filed Mar 14, 2025
04/07/2025 S Referred to Business & Commerce
Texas Legislature Online · Introduced
Data snapshot Oct 26, 2026 at 4:20 AM CDT. Grades, charges, quotes and corrections follow the published record.
Senate committee · Business & Commerce · Final status: Died in committee
Companion
HB 3092 by Gerdes (identical)
Subjects
Utilities--Electric
Text
The text as introduced · 179 words
89R9042 SCR-D By: Sparks S.B. No. 2930 A BILL TO BE ENTITLED AN ACT relating to a certificate of public convenience and necessity to construct an electric transmission line. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: SECTION 1. Section 37.052(c), Utilities Code, is amended to read as follows: (c) An electric utility is not required to amend the utility's certificate of public convenience and necessity to construct a transmission line that connects the utility's existing transmission facilities to a substation or metering point if: (1) the transmission line does not exceed: (A) five [ three ] miles in length, if the line connects to a load-serving substation or metering point; or (B) two miles in length, if the line connects to a generation substation or metering point; (2) each landowner whose property would be directly affected by the transmission line, as provided by commission rules, provides written consent for the transmission line; and (3) all rights-of-way necessary for construction of the transmission line have been purchased. SECTION 2. This Act takes effect September 1, 2025.