Kolkhorst Bill Makes Wind And Solar Projects Apply To Connect

Died in committee

Verdict: Smells

SmellsReviewed
Sen. Lois KolkhorstRSenate 18
Why it's charged
New fee, fund, board or appointees

THE TEXT

“The commission may impose an application fee to cover the costs associated with reviewing an application filed under this section.”

Bill text, Senate committee report version (S)

The bill creates a new application fee at the Public Utility Commission. The caption openly says it authorizes fees, so this is honest but still a new charge.

New fee, fund, board or appointees

Reviewed · Nov 1, 2026 · Headline, summary and grade are analysis of the bill text, not a finding about any person · How we grade

Caption

relating to renewable energy generation facilities; authorizing fees.

Caption from analyzed text · version S.

Summary

Covers 10 megawatts or more. The commission gets 180 days. Silence means approved!

The bill requires anyone who wants to connect a wind or solar project of 10 megawatts or more to the transmission grid to first file an application with the Public Utility Commission. The application must include a site plan with waivable setbacks from neighbors, proof of a bond under any existing wind or solar agreement, and proof of public notice to nearby county judges and in local newspapers, and the commission may charge a fee to review it. The commission has 180 days to act and may deny only if harm substantially outweighs benefit to the state or the application is incomplete; if it does nothing, the project is approved automatically.

Labels

Labels: FEE INCLUDED. The caption of the graded version (Senate committee report) reads: “relating to renewable energy generation facilities; authorizing fees.”ACROSS THE AISLE. Joint authors: 9 Republicans, 1 Democrat. Party as the Legislative Reference Library lists it for the 89th Legislature.GOT HALFWAY. Passed the Senate on Apr 15, 2025. Died in the House: never got out of the State Affairs committee.

Receipt

The receipt

89R-SB819 · 2025-01-16

SOLD BY

+ 7 more authors, 1 coauthor

ITEM

relating to renewable energy generation facilities; authorizing fees.

WHAT IT DOES

Covers 10 megawatts or more. The commission gets 180 days. Silence means approved!

The bill requires anyone who wants to connect a wind or solar project of 10 megawatts or more to the transmission grid to first file an application with the Public Utility Commission. The application must include a site plan with waivable setbacks from neighbors, proof of a bond under any existing wind or solar agreement, and proof of public notice to nearby county judges and in local newspapers, and the commission may charge a fee to review it. The commission has 180 days to act and may deny only if harm substantially outweighs benefit to the state or the application is incomplete; if it does nothing, the project is approved automatically.

CHARGES

[x] NEW FEE, FUND, BOARD OR APPOINTEESanalysis confidence 40%

THE TEXT

“The commission may impose an application fee to cover the costs associated with reviewing an application filed under this section.”

Bill text, Senate committee report version (S)

The bill creates a new application fee at the Public Utility Commission. The caption openly says it authorizes fees, so this is honest but still a new charge.

TOTAL

Net to General Revenue · FY 2026$0

LBB estimate, flow · fiscal note version S · ( ) = negative · source

Sources

Fiscal note · version S · April 7, 2025

Estimated Two-year Net Impact to General Revenue Related Funds for SB819, Committee Report 1st House, Substituted: an impact of $0 through the biennium ending August 31, 2027. The bill would make no appropriation but could provide the legal basis for an appropriation of funds to implement the provisions of the bill.

First year · FY 2026 · $0

Probable Net Positive/(Negative) Impact to General Revenue Related Funds

LBB published estimates · flow over the stated periods.

Source snapshot 2026-10-19, Central time.

HISTORY

  1. Received by the Secretary of the Senate
  2. Filed
  3. Read first time
  4. Referred to Business & Commerce
  5. Scheduled for public hearing on . . .
  6. Considered in public hearing
  7. Testimony taken in committee
  8. Left pending in committee
  9. Considered in public hearing
  10. Vote taken in committee
  11. Reported favorably as substituted
  12. Committee report printed and distributed
  13. Placed on intent calendar
  14. Co-author authorized
  15. Rules suspended-Regular order of business
  16. Record vote
  17. Read 2nd time
  18. Amendment(s) offered FA1 Kolkhorst
  19. Amended
  20. Vote recorded in Journal
  21. Amendment(s) offered FA2 Hall
  22. Amended
  23. Vote recorded in Journal
  24. Passed to engrossment as amended
  25. Record vote
  26. Three day rule suspended
  27. Record vote
  28. Read 3rd time
  29. Passed
  30. Record vote
  31. Reported engrossed
  32. Received from the Senate
  33. Read first time
  34. Referred to State Affairs
FILED UNDER

DATA CENTERS, WATER AND THE GRID

THE TEXT

“A person may not interconnect a renewable energy generation facility with a capacity of 10 megawatts or more to a transmission facility unless the person files an application for a determination of public interest with the commission.”

Bill text, Senate committee report version (S)

The bill puts a new state review step in front of large wind and solar projects before they can connect to the grid.

SIGNED FOR BY

Senate · 22 yea · 9 nay

Sources

Senate: Final passage · Apr 15, 2025. Journal. Published stock for this vote. Snapshot 2026-10-19, Central time.

All floor motions and other positions below.

Smells

THANK YOU FOR CHECKING THE RECEIPT

CAMPAIGN PAID FOR BY

CAMPAIGN PAID FOR BY

Donors

Not tied to this bill.

Sources

The author's campaign account only. Own money and internal transfers are separate on the member page.

Derived itemized flow · Jul 11, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Texans for Lawsuit Reform PAC$60,000.00

Texans for Lawsuit Reform PAC

$60,000.00

Cash
$60,000.00
Paid by others
$0.00
Total
$60,000.00

Also funds 124 other sitting lawmakers.

Derived recipient stock · Jul 10, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Nov 19, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101007416, 101012417, 101070754.

Border Health PAC$35,000.00

Border Health PAC

$35,000.00

Cash
$35,000.00
Paid by others
$0.00
Total
$35,000.00

Also funds 17 other sitting lawmakers.

Derived recipient stock · Oct 28, 2024 to Aug 26, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · on Dec 6, 2024. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101012417.

SRR Ranches, LLC$30,000.00

SRR Ranches, LLC

$30,000.00

Cash
$30,000.00
Paid by others
$0.00
Total
$30,000.00

Also funds 3 other sitting lawmakers.

Derived recipient stock · Oct 23, 2024 to Oct 8, 2026. State data as of Nov 4, 2026.

Name match, not a verified identity: normalized filed name and state.

Sources

Derived itemized flow · Oct 23, 2024 to Oct 1, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101012417, 101070754.

Money

Missing data does not establish zero giving. Display amounts are rounded.

×

Texans for Lawsuit Reform PAC

$60,000.00

Cash
$60,000.00
Paid by others
$0.00
Total
$60,000.00

Also funds 124 other sitting lawmakers.

Derived recipient stock · Jul 10, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Nov 19, 2024 to Oct 23, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101007416, 101012417, 101070754.

×

Border Health PAC

$35,000.00

Cash
$35,000.00
Paid by others
$0.00
Total
$35,000.00

Also funds 17 other sitting lawmakers.

Derived recipient stock · Oct 28, 2024 to Aug 26, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · on Dec 6, 2024. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101012417.

×

SRR Ranches, LLC

$30,000.00

Cash
$30,000.00
Paid by others
$0.00
Total
$30,000.00

Also funds 3 other sitting lawmakers.

Derived recipient stock · Oct 23, 2024 to Oct 8, 2026. State data as of Nov 4, 2026.

Name match, not a verified identity: normalized filed name and state.

Sources

Derived itemized flow · Oct 23, 2024 to Oct 1, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101012417, 101070754.

Votes5

Senate Apr 15, 2025

Yea
22
Nay
9
Present, not voting
Not printed
Absent
0
Excused
0
Names

Named positions matched to lawmakers. See the journal for unmatched names.

Senate journal

Sources

The bill was read third time and was passed by the following vote: Yeas 22, Nays 9.

Published stock of positions for this vote, except where marked derived.

  • Yea: 22 (published)
  • Nay: 9 (published)
  • Present, not voting: Not printed
  • Absent: 0 (derived from named list)
  • Excused: 0 (derived from named list)

Senate journal. Source snapshot 2026-10-19, Central time.

Senate Apr 15, 2025

Yea
25
Nay
6
Present, not voting
Not printed
Absent
0
Excused
0
Names

Named positions matched to lawmakers. See the journal for unmatched names.

Senate journal

Sources

Senator Kolkhorst moved that Senate Rule 7.18 and the Constitutional Rule requiring bills to be read on three several days be suspended and that CSSB 819 be placed on its third reading and final passage: CSSB 819, Relating to renewable energy generation facilities; authorizing fees. The motion prevailed by the following vote: Yeas 25, Nays 6.

Published stock of positions for this vote, except where marked derived.

  • Yea: 25 (published)
  • Nay: 6 (published)
  • Present, not voting: Not printed
  • Absent: 0 (derived from named list)
  • Excused: 0 (derived from named list)

Senate journal. Source snapshot 2026-10-19, Central time.

Senate Apr 15, 2025

Yea
22
Nay
9
Present, not voting
Not printed
Absent
0
Excused
0
Names

Named positions matched to lawmakers. See the journal for unmatched names.

Senate journal

Sources

CSSB 819 as amended was passed to engrossment by the following vote: Yeas 22, Nays 9.

Published stock of positions for this vote, except where marked derived.

  • Yea: 22 (published)
  • Nay: 9 (published)
  • Present, not voting: Not printed
  • Absent: 0 (derived from named list)
  • Excused: 0 (derived from named list)

Senate journal. Source snapshot 2026-10-19, Central time.

Senate Apr 15, 2025

Yea
Not printed
Nay
Not printed
Present, not voting
Not printed
Absent
Not printed
Excused
Not printed
Names

Named positions matched to lawmakers. See the journal for unmatched names.

Senate journal

Names were not printed for yea. Only the named positions are included in member records.

Voice vote. No numeric tally or individual yeas are inferred.

Sources

The amendment to CSSB 819 was read and was adopted by a viva voce vote.

Published stock of positions for this vote, except where marked derived.

  • Yea: Not printed
  • Nay: Not printed
  • Present, not voting: Not printed
  • Absent: Not printed
  • Excused: Not printed

Senate journal. Source snapshot 2026-10-19, Central time.

Senate Apr 15, 2025

Yea
22
Nay
9
Present, not voting
Not printed
Absent
0
Excused
0
Names

Named positions matched to lawmakers. See the journal for unmatched names.

Senate journal

Sources

Senator Kolkhorst moved to suspend the regular order of business to take up for consideration CSSB 819 at this time on its second reading: CSSB 819, Relating to renewable energy generation facilities; authorizing fees. The motion prevailed by the following vote: Yeas 22, Nays 9.

Published stock of positions for this vote, except where marked derived.

  • Yea: 22 (published)
  • Nay: 9 (published)
  • Present, not voting: Not printed
  • Absent: 0 (derived from named list)
  • Excused: 0 (derived from named list)

Senate journal. Source snapshot 2026-10-19, Central time.

Witnesses128
For
20
Against
104
On
4
Names

For

  • Self7 registrations
  • Self; American Energy Works1 registration
  • Self; FayCoSaysNo1 registration
  • Self; Franklin County Environmental Group2 registrations
  • Self; Plaintiffs in lawsuit concerning Fayette County BESS1 registration
  • Self; Secure the Grid Committee2 registrations
  • Self; Texas Eagle Forum1 registration
  • Self; Texas Foundation for Conservation1 registration
  • Self; Texas Wildlife Association1 registration
  • Texas Agricultural Aviation Association1 registration
  • Texas Chapter of The Wildlife Society1 registration
  • Texas Farm Bureau1 registration

Against

  • Acciona Energy USA1 registration
  • Advanced Power Alliance1 registration
  • AES Corp.1 registration
  • American Clean Power Association1 registration
  • American Lung Association1 registration
  • Association of Electric Companies of Texas1 registration
  • Audubon Texas/National Audubon Society1 registration
  • Avangrid1 registration
  • BASF Corporation1 registration
  • County Judges and Commissioners Association of Texas1 registration
  • Cypress Creek Renewables1 registration
  • Defenders of Wildlife1 registration
  • EDF Renewables1 registration
  • EDP Renewables North America1 registration
  • Enbridge1 registration
  • Enel North America, Inc.1 registration
  • Engie North America1 registration
  • Environment Texas2 registrations
  • Environmental Defense Fund1 registration
  • Farm&City1 registration
  • Intersect Power1 registration
  • Leeward Renewable Energy1 registration
  • Lightsource BP1 registration
  • Lone Star Chapter Sierra Club1 registration
  • Moss and Associates1 registration
  • MOVE Texas Civic Fund1 registration
  • Nexamp1 registration
  • NextEra Energy1 registration
  • North Texas Commission1 registration
  • Pattern Energy Group 2 LP1 registration
  • Public Citizen1 registration
  • R Street Institute1 registration
  • RWE1 registration
  • Savion Energy1 registration
  • Self38 registrations
  • Self; Advanced Power Alliance1 registration
  • Self; American Conservation Coalition Action1 registration
  • Self; Apex Clean Energy1 registration
  • Self; Audubon Texas1 registration
  • Self; Austin Chamber of Commerce1 registration
  • Self; Caprock Renewables1 registration
  • Self; Citizens Climate Lobby1 registration
  • Self; Climate Cabinet1 registration
  • Self; Conservative Texans for Energy Innovation1 registration
  • Self; Conservative Texans for Energy Innovation (CTEI)1 registration
  • Self; Earthworks1 registration
  • Self; Environment Texas1 registration
  • Self; Invenergy LLC1 registration
  • Self; OCI Energy1 registration
  • Self; Project Vanguard1 registration
  • Self; San Angelo Chamber of Commerce1 registration
  • Self; Sierra Club Lone Star Chapter1 registration
  • Self; Texas Impact1 registration
  • Self; Texas Solar Energy Society1 registration
  • Self; Water Valley School Board1 registration
  • Society of Native Nations1 registration
  • Sol Systems, LLC1 registration
  • Solar Energy Industries Association (SEIA)1 registration
  • Texas Advanced Energy Business Alliance1 registration
  • Texas Association of Business1 registration
  • Texas Economic Development Council1 registration
  • Texas Energy Buyers Association1 registration
  • Texas Solar and Storage Association1 registration
  • Vestas American Wind Technology, Inc1 registration
  • Walmart1 registration
  • Ørsted1 registration

On

  • Harris County Commissioners Court1 registration
  • Public Utility Commission of Texas1 registration
  • Self1 registration
  • Texas Parks and Wildlife Department1 registration
Sources

128 parsed registrations across the loaded witness lists.

Derived stock of witness registrations. Repeated appearances count separately. Organizations and self-representation appear as printed.

Senate witness list. Source snapshot 2026-10-20, Central time.

Fiscal
Net to General Revenue · FY 2026$0

LBB estimate, flow · fiscal note version S · ( ) = negative · source

Sources

Fiscal note · version S · April 7, 2025

Estimated Two-year Net Impact to General Revenue Related Funds for SB819, Committee Report 1st House, Substituted: an impact of $0 through the biennium ending August 31, 2027. The bill would make no appropriation but could provide the legal basis for an appropriation of funds to implement the provisions of the bill.

First year · FY 2026 · $0

Probable Net Positive/(Negative) Impact to General Revenue Related Funds

LBB published estimates · flow over the stated periods.

Source snapshot 2026-10-19, Central time.

How this was graded

Analysis of text version S by claude-opus-5-5, Oct 22, 2026, against the published rubric.

Sources

Texas Senate · Filed Jan 16, 2025

04/22/2025 H Referred to State Affairs: Apr 22 2025 3:20PM

Texas Legislature Online · Introduced · Senate Committee Report · Engrossed

Data snapshot Nov 1, 2026 at 3:16 PM CST. Grades, charges, quotes and corrections follow the published record.

Coauthors

House committee · State Affairs · Final status: Died in committee

Senate committee · Business & Commerce · Committee vote 7 aye, 4 nay · Out of committee

Subjects

Energy--General

Energy--Solar

Energy--Wind (IA9YE)

Fees & Other Nontax Revenue--State

Parks & Wildlife--General

Taxation--Property-Miscellaneous

Utilities--Electric

PERMITS

RENEWABLE ENERGY

PARKS & WILDLIFE DEPARTMENT

PUBLIC UTILITY COMMISSION

Text

The text as introduced · 2,334 words

89R5788 SCR/CJC-F

By: Kolkhorst, et al.
S.B. No. 819

A BILL TO BE ENTITLED

AN ACT

relating to renewable energy generation facilities; authorizing

fees.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

SECTION 1. Chapter 35, Utilities Code, is amended by adding

Subchapter F to read as follows:

SUBCHAPTER F. RENEWABLE ENERGY GENERATION FACILITY PERMIT

Sec. 35.201. DEFINITIONS; APPLICABILITY. (a) In this

subchapter:

(1) "Permit holder" means a person who holds a permit

issued under this subchapter.

(2) "Person" includes an electric cooperative and a

municipally owned utility.

(3) "Renewable energy generation facility" means:

(A) a wind power facility as defined by Section

301.0001; or

(B) a solar power facility as defined by Section

302.0001.

(b) This subchapter applies to a renewable energy

generation facility regardless of whether the facility is the

subject of a wind power facility agreement or solar power facility

agreement entered into under Chapter 301 or 302.

(c) This subchapter does not apply to a solar power facility

located in the corporate boundaries of a home-rule municipality.

Sec. 35.202. LEGISLATIVE POLICY AND PURPOSE. The

conservation and development of all the natural resources of this

state are declared to be public rights and duties. It is also

declared that balancing private property rights, the need to

increase electric generation, and the need to mitigate unreasonable

impacts of renewable energy generation facilities on wildlife,

water, and land in this state is in the public interest. In the

exercise of the police power of this state, it is necessary and

desirable to provide additional means so that the installation and

removal of renewable energy generation facilities is placed under

the authority and direction of the commission.

Sec. 35.203. PERMIT REQUIRED; APPLICATION. (a) A person

may not interconnect a renewable energy generation facility with a

capacity of 10 megawatts or more to a transmission facility unless:

(1) the person holds a permit to operate a renewable

energy generation facility issued by the commission under this

subchapter; or

(2) the commission by order approves the construction

of the generation facility.

(b) A person may apply for a permit to operate a renewable

energy generation facility by filing with the commission:

(1) a description of the location of the facility;

(2) a description of the type of facility;

(3) a copy of any information filed with the Federal

Energy Regulatory Commission in connection with registration with

that commission;

(4) any assumed business or professional name of the

applicant filed under Chapter 71, Business & Commerce Code;

(5) an environmental impact review conducted by the

Parks and Wildlife Department under Section 12.0012, Parks and

Wildlife Code;

(6) any wind power facility agreement or solar power

facility agreement applicable to the facility entered into under

Chapter 301 or 302 by the applicant;

(7) the address of an Internet website that provides

information about the proposed facility; and

(8) any other information required by commission rule,

provided that in requiring that information the commission shall

protect the competitive process in a manner that ensures the

confidentiality of competitively sensitive information.

(c) Notwithstanding Subsection (a), a person who

interconnected a renewable energy generation facility to a

transmission facility before September 1, 2025, must apply for a

permit under this subchapter only if the person:

(1) increases the amount of electricity generated by

the facility by five megawatts or more; or

(2) materially changes the placement of the renewable

energy generation facility.

Sec. 35.204. NOTICE AND MEETING. (a) The commission by rule

shall require an applicant for a permit or a permit amendment to:

(1) provide notice of the application to the county

judge of each county located within 25 miles of the boundary of the

renewable energy generation facility that is the subject of the

permit;

(2) hold a public meeting to obtain public input on the

proposed permit or permit amendment; and

(3) after applying for the permit or permit amendment,

publish for at least two consecutive publications in a newspaper of

general circulation in each county in which the renewable energy

generation facility that is the subject of the permit will be or is

located a notice that includes:

(A) the time and place of the public meeting; and

(B) a link to a publicly accessible Internet

website that provides information about the facility and

information regarding the public meeting.

(b) A public meeting held under this section must be held in

a location that is:

(1) not more than 25 miles from the boundary of the

renewable energy generation facility that is the subject of the

permit; or

(2) if a suitable meeting place is not available in a

location described by Subdivision (1), in the nearest suitable

meeting location.

(c) The commission may not approve or deny an application

for a permit or permit amendment before the 30th day after the date

the applicant conducts the public meeting required by this section.

(d) Notwithstanding any other provision of this subchapter,

the commission may approve an application to amend a permit without

requiring a public meeting if:

(1) the applicant is not applying to:

(A) significantly increase the amount of

electricity generated under the permit; or

(B) materially change the placement of the

renewable energy generation facility;

(2) the commission determines that the applicant's

compliance history raises no issues regarding the applicant's

ability to comply with a material term of the permit; and

(3) the commission:

(A) gives notice of the application to the county

judge of each county and the governing body of each municipality in

which the facility is located at least 30 days before the date of

the commission's approval of the application; and

(B) allows the county judges and governing bodies

to present information to the commission on the application.

Sec. 35.205. APPROVAL OR DENIAL OF APPLICATION. (a) The

commission may approve an application only if the commission finds

that issuance or amendment of the permit would not violate state or

federal law or rule and would not interfere with the purpose of this

subchapter.

(b) In considering an application for the issuance or

amendment of a permit, the commission shall consider the compliance

history of the applicant.

(c) A permit holder does not have a vested right in a permit.

Sec. 35.206. CONDITIONS OF PERMIT. (a) For each permit,

the commission shall prescribe the conditions under which it is

issued, including:

(1) the boundary of the permitted facility location;

(2) the maximum number of renewable energy generation

facilities authorized by the permit; and

(3) any monitoring and reporting requirements

prescribed by the commission for the permit holder.

(b) The commission, on its own motion after reasonable

notice and hearing, may require a permit holder to conform to new or

additional conditions to comply with this subchapter or rules

adopted under this subchapter.

(c) A permit holder shall:

(1) for a solar power facility, ensure that all

permitted facility equipment is located at least:

(A) 100 feet from any property line, unless the

permit holder has obtained a written waiver from each owner of

property located less than 100 feet from the permitted facility;

and

(B) 200 feet from any habitable structure, unless

the permit holder has obtained a written waiver from each owner of

the habitable structure;

(2) for a wind power facility, ensure that all

permitted facility equipment is located at least 3,000 feet from

the property line of each property that borders the property on

which the permitted facility is located, unless the permit holder

has obtained a written waiver from each owner of property located

less than 3,000 feet from the permitted facility;

(3) provide a publicly accessible Internet website

that displays:

(A) a map of the boundaries of the permitted

facility;

(B) any interconnection request numbers assigned

to the permitted facility;

(C) the name of the owner of the permitted

facility; and

(D) any other information required by the

commission; and

(4) provide evidence to the commission that the permit

holder has complied with Chapter 301 or 302, as applicable, by

providing financial assurance in the form of a bond.

(d) The distance from the property line required by

Subsection (c)(2) must be measured as a straight line from the

vertical centerline of the wind turbine to the nearest point on the

property line.

Sec. 35.207. MONITORING AND REPORTING. The commission by

rule may, in coordination with the Parks and Wildlife Department,

require a permit holder to:

(1) monitor, record, and report on environmental

impacts created by the permitted facility;

(2) conduct wildlife assessments around the permitted

facility and provide assessment results to the Parks and Wildlife

Department in a form and according to deadlines required by the

department;

(3) adapt operations based on information obtained

under Subdivisions (1) and (2) to minimize facility effects on

bats, birds, and other wildlife; and

(4) provide to the commission and the Parks and

Wildlife Department other information about the operation of the

permitted facility.

Sec. 35.208. RENEWABLE ENERGY GENERATION FACILITY CLEANUP

FUND. (a) The renewable energy generation facility cleanup fund is

a dedicated account in the general revenue fund.

(b) The fund consists of:

(1) environmental impact fees collected under Section

35.209;

(2) gifts, grants, and donations; and

(3) legislative appropriations.

(c) Money in the fund may be used only by the commission to

implement this subchapter.

Sec. 35.209. ENVIRONMENTAL IMPACT FEE. (a) An annual

environmental impact fee is imposed on each permit holder.

(b) Environmental impact fees must be deposited in the

renewable energy generation facility cleanup fund.

(c) The fee for each year is imposed on each permit in effect

during any part of the year. The commission may establish reduced

fees for inactive permits.

(d) The commission by rule shall adopt a fee schedule for

determining the amount of the fee to be charged. In determining the

amount of a fee under this section, the commission may consider:

(1) the efficiency of the renewable energy generation

facility;

(2) the area and size of the renewable energy

generation facility;

(3) the renewable energy generation facility's

environmental impact score provided under Section 12.0012, Parks

and Wildlife Code; and

(4) expenses necessary to implement this subchapter.

Sec. 35.210. FEDERAL FUNDS. The commission may execute

agreements with the United States Environmental Protection Agency

or any other federal agency that administers programs providing

federal cooperation, assistance, grants, or loans for research,

development, investigation, training, planning, studies,

programming, or construction related to methods, procedures,

mitigation, and facilities for the removal of renewable energy

generation facilities. The commission may accept federal funds for

these purposes and for other purposes consistent with the

objectives of this subchapter and may use the funds as prescribed by

law or as provided by agreement.

Sec. 35.211. POWER TO REGULATE AND SUPERVISE. (a) For

purposes of this subchapter, a provision of Subchapter B or E,

Chapter 14, that authorizes the commission to regulate a public

utility also applies to a person required to obtain a permit under

this subchapter, including an electric cooperative and a

municipally owned utility.

(b) The commission may adopt and enforce rules reasonably

required in the exercise of its powers under this subchapter.

Sec. 35.212. ENFORCEMENT AND PENALTIES. For the purposes

of enforcing this subchapter, a reference in Chapter 15 to a person

includes any person required to obtain a permit under this

subchapter, including an electric cooperative and a municipally

owned utility.

SECTION 2. Subchapter A, Chapter 12, Parks and Wildlife

Code, is amended by adding Section 12.0012 to read as follows:

Sec. 12.0012. ENVIRONMENTAL IMPACT REVIEW FOR RENEWABLE

ENERGY GENERATION FACILITIES. The commission by rule shall adopt a

system for providing an environmental impact review in a format

established by the commission to an applicant for a renewable

energy generation facility permit under Section 35.203, Utilities

Code, based on materials provided by the applicant. The system must

establish:

(1) a process for a person to apply for and receive

from the department an environmental impact review;

(2) criteria for the department to evaluate the

environmental impact of a proposed renewable energy generation

facility, including:

(A) the facility's prioritization of natural

resource conservation, wildlife conservation management, and

agricultural use of land;

(B) use of the land on which the facility is

located for agricultural purposes;

(C) the applicant's commitment to and planned

implementation of avoidance and minimization measures to conserve

natural resources; and

(D) agricultural best practices developed by the

department in coordination with the Texas A&M AgriLife Extension

Service;

(3) a method for the department to provide an

environmental impact score for a renewable energy generation

facility, based on the criteria described by Subdivision (2);

(4) fees for providing the environmental impact

reviews, in an amount sufficient to cover the department's costs of

implementing this section; and

(5) guidelines for the department's use of any map

applications necessary for the implementation of this section,

including the applicant's mapping of specific areas and other

aspects required by the department to produce an effective and

timely review.

SECTION 3. Subchapter A, Chapter 312, Tax Code, is amended

by adding Section 312.0022 to read as follows:

Sec. 312.0022. PROHIBITION ON ABATEMENT OF TAXES ON CERTAIN

RENEWABLE ENERGY GENERATION FACILITY PROPERTY. (a) In this

section, "renewable energy generation facility" has the meaning

assigned by Section 35.201, Utilities Code.

(b) This section applies only to a renewable energy

generation facility that has or will have a generation capacity of

10 megawatts or more.

(c) The governing body of a taxing unit may not enter into an

agreement under this chapter to exempt from taxation a portion of

the value of real property on which a renewable energy generation

facility is located or is planned to be located during the term of

the agreement, or of tangible personal property that is located or

is planned to be located on the real property during that term.

SECTION 4. Section 312.0022, Tax Code, as added by this Act,

applies only to an agreement entered into under Chapter 312, Tax

Code, on or after the effective date of this Act.

SECTION 5. This Act takes effect September 1, 2025.