Monitoring the Session

SB 1216

Eckhardt Gas Well Bill Lets Operators Call Capture ‘Commercially Unfeasible’

Died in committee

Verdict: Smells

SmellsInitial review
Sen. Sarah EckhardtDSenate 14
Why it's charged
The hole

THE TEXT

…“connection to a pipeline is technically or commercially unfeasible;”

Bill text, introduced version (I)

The good faith effort test is met largely on the operator's own finding that capturing or using the gas is commercially unfeasible. That could let routine flaring keep getting permits under the new requirement.

The hole

Initial review · graded Oct 20, 2026 · Headline, summary and grade are analysis of the bill text, not a finding about any person · How we grade

Caption

relating to the authority of the Railroad Commission of Texas to permit the release into the air of natural gas from a gas well.

Caption from analyzed text · version I.

Summary

Flaring past 10 days needs a good faith effort, met largely by the operator’s own finding.

The bill lets the Railroad Commission allow gas to be vented or flared past the first 10 days only if the operator shows the release is necessary and that it made a good faith, commercially reasonable effort to capture, sell or otherwise use the gas. It touches gas well operators and the Railroad Commission, and it spells out when an operator counts as having made that effort: no adequate pipeline access, and on-site use and other productive uses judged unfeasible. The commission must write rules by December 1, 2025, and the law takes effect September 1, 2025.

Labels

Labels: NEVER GOT A HEARING. Filed Feb 11, 2025 and referred to the Senate Natural Resources committee. No public hearing. The bill died.

Receipt

The receipt

89R-SB1216 · 2025-02-11

SOLD BY

ITEM

relating to the authority of the Railroad Commission of Texas to permit the release into the air of natural gas from a gas well.

WHAT IT DOES

Flaring past 10 days needs a good faith effort, met largely by the operator’s own finding.

The bill lets the Railroad Commission allow gas to be vented or flared past the first 10 days only if the operator shows the release is necessary and that it made a good faith, commercially reasonable effort to capture, sell or otherwise use the gas. It touches gas well operators and the Railroad Commission, and it spells out when an operator counts as having made that effort: no adequate pipeline access, and on-site use and other productive uses judged unfeasible. The commission must write rules by December 1, 2025, and the law takes effect September 1, 2025.

CHARGES

[x] THE HOLEanalysis confidence 40%

THE TEXT

…“connection to a pipeline is technically or commercially unfeasible;”

Bill text, introduced version (I)

The good faith effort test is met largely on the operator's own finding that capturing or using the gas is commercially unfeasible. That could let routine flaring keep getting permits under the new requirement.

TOTAL

No fiscal note in the loaded record.

HISTORY

  1. Received by the Secretary of the Senate
  2. Filed
  3. Read first time
  4. Referred to Natural Resources
FILED UNDER

No verified beat found.

Smells

THANK YOU FOR CHECKING THE RECEIPT

CAMPAIGN PAID FOR BY

CAMPAIGN PAID FOR BY

Donors

Donald Henley$117,500Dale Linebarger$38,769Stephen McNally$24,000

Not tied to this bill.

Sources

The author's campaign account only. Own money and internal transfers are separate on the member page.

Derived itemized flow · Jul 1, 2024 to Oct 24, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Donald Henley$117,500.00
Dale Linebarger$38,769.25
Stephen McNally$24,000.00
Money

Missing data does not establish zero giving. Display amounts are rounded.

Votes

No floor vote loaded for this bill.

Fiscal

No fiscal note in the loaded record.

How this was graded

Analysis of text version I by claude-opus-5-5, Oct 20, 2026, against the published rubric.

Sources

Texas Senate · Filed Feb 11, 2025

02/28/2025 S Referred to Natural Resources

Texas Legislature Online · Introduced

Data snapshot Oct 26, 2026 at 4:20 AM CDT. Grades, charges, quotes and corrections follow the published record.

Senate committee · Natural Resources · Final status: Died in committee

Subjects

Environment--Air

Oil & Gas

RAILROAD COMMISSION

Text

The text as introduced · 457 words

89R4130 CMO-F

By: Eckhardt
S.B. No. 1216

A BILL TO BE ENTITLED

AN ACT

relating to the authority of the Railroad Commission of Texas to

permit the release into the air of natural gas from a gas well.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

SECTION 1. Section 86.185, Natural Resources Code, is

amended to read as follows:

Sec. 86.185. PROHIBITION AGAINST GAS IN AIR. (a) No gas

from a gas well may be permitted to escape into the air after the

expiration of 10 days from the time the gas is encountered in the

gas well, or from the time of perforating the casing opposite a

gas-bearing zone if casing is set through the zone, whichever is

later, but the commission may permit the escape of gas into the air

for an additional time if :

(1) the operator of a well or other facility presents

information to show :

(A) the necessity for the escape; and

(B) the operator made a good faith and

commercially reasonable effort to capture and sell the gas, or

otherwise use the gas for another productive purpose, as defined by

commission rule; and

(2) [ provided that ] the amount of gas which is flared

under the [ that ] commission's authority is charged to the

operator's allowable production.

(b) For the purposes of Subsection (a):

(1) a [ A ] necessity includes [ but is not limited to the

following situations ]:

(A) [ (1) ] cleaning a well of sand or acid or both

following stimulation treatment of a well; and

(B) [ (2) ] repairing or modifying a gas-gathering

system ; and

(2) an operator of a well or other facility is

considered to have made a good faith and commercially reasonable

effort if:

(A) the well is:

(i) connected to a pipeline on which

pipeline takeaway capacity is not expected to meet the demand for

gas produced from the well; or

(ii) not connected to a pipeline and

connection to a pipeline is technically or commercially unfeasible;

(B) the operator evaluated options for on-site

consumption of the gas and determined:

(i) on-site consumption of the gas is

technically or commercially unfeasible; or

(ii) commercial interest in on-site

consumption does not meet the demand for gas produced from the well;

and

(C) the operator evaluated options to use the gas

for another productive purpose and determined it would be

technically or commercially unfeasible.

(c) The commission shall adopt rules necessary to implement

this section .

SECTION 2. Not later than December 1, 2025, the Railroad

Commission of Texas shall adopt rules necessary to implement

Section 86.185, Natural Resources Code, as amended by this Act.

SECTION 3. This Act takes effect September 1, 2025.