SB 1942

Parker Bill Fast-Tracks 75-Megawatt Users Who Agree To Unplug

Died in committee

Verdict: No flags

No flagsInitial review
Sen. Tan ParkerRSenate 12

Initial review · graded Oct 20, 2026 · Headline, summary and grade are analysis of the bill text, not a finding about any person · How we grade

Caption

relating to electricity planning for large loads.

Caption from analyzed text · version I.

Summary

Run on your own generation when ERCOT calls, and you move up the connection line.

The bill orders the Public Utility Commission to have ERCOT build a fast-track program for connecting very large power users, generally 75 megawatts or more at one site, to the grid. Large users who agree to stop drawing grid power and run their own on-site generation when ERCOT says so get moved ahead in the connection line, especially if they will also sell their on-site power back to the grid or cut use to a set minimum. These users can also hire approved vendors for the required studies, buy their own equipment and build their own connection facilities, and utilities may plan for them as power that can be cut off.

Labels

Labels: NEVER GOT A HEARING. Filed Mar 5, 2025 and referred to the Senate Business & Commerce committee. No public hearing. The bill died.

Receipt

The receipt

89R-SB1942 · 2025-03-05

SOLD BY

ITEM

relating to electricity planning for large loads.

WHAT IT DOES

Run on your own generation when ERCOT calls, and you move up the connection line.

The bill orders the Public Utility Commission to have ERCOT build a fast-track program for connecting very large power users, generally 75 megawatts or more at one site, to the grid. Large users who agree to stop drawing grid power and run their own on-site generation when ERCOT says so get moved ahead in the connection line, especially if they will also sell their on-site power back to the grid or cut use to a set minimum. These users can also hire approved vendors for the required studies, buy their own equipment and build their own connection facilities, and utilities may plan for them as power that can be cut off.

CHARGES

[ ] NONE FOUND

TOTAL

No fiscal note in the loaded record.

HISTORY

  1. Received by the Secretary of the Senate
  2. Filed
  3. Read first time
  4. Referred to Business & Commerce
FILED UNDER

DATA CENTERS, WATER AND THE GRID

THE TEXT

…“provide an expedited interconnection process for operators of large”…

Bill text, introduced version (I)

Large power users that agree to switch to their own generation when ERCOT directs get priority in the grid connection line ahead of other applicants.

No flags

THANK YOU FOR CHECKING THE RECEIPT

CAMPAIGN PAID FOR BY

CAMPAIGN PAID FOR BY

Donors

Not tied to this bill.

Sources

The author's campaign account only. Own money and internal transfers are separate on the member page.

Derived itemized flow · Oct 28, 2024 to Jun 29, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Texas Stock Exchange | TXSE Group PAC$40,000.00

Texas Stock Exchange | TXSE Group PAC

$40,000.00

Cash
$40,000.00
Paid by others
$0.00
Total
$40,000.00

Also funds 10 other sitting lawmakers.

Derived recipient stock · Feb 17, 2026 to Oct 16, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Feb 17, 2026 to Jun 25, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101060289.

Texas REALTORS Political Action Committee$25,250.00

Texas REALTORS Political Action Committee

$25,250.00

Cash
$25,000.00
Paid by others
$250.00
Total
$25,250.00
fundraiser $250.00

Also funds 140 other sitting lawmakers.

Derived recipient stock · Jul 2, 2024 to Oct 24, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Dec 4, 2024 to Oct 9, 2025. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 100986801, 101009904, 101031351.

The Peck Family Trust$25,000.00

The Peck Family Trust

$25,000.00

Cash
$25,000.00
Paid by others
$0.00
Total
$25,000.00

Also funds 1 other sitting lawmakers.

Derived recipient stock · Dec 14, 2024 to Sep 18, 2026. State data as of Nov 4, 2026.

Name match, not a verified identity: normalized filed name and state.

Sources

Derived itemized flow · on Dec 14, 2024. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 100986801.

Money

Missing data does not establish zero giving. Display amounts are rounded.

×

Texas Stock Exchange | TXSE Group PAC

$40,000.00

Cash
$40,000.00
Paid by others
$0.00
Total
$40,000.00

Also funds 10 other sitting lawmakers.

Derived recipient stock · Feb 17, 2026 to Oct 16, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Feb 17, 2026 to Jun 25, 2026. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 101060289.

×

Texas REALTORS Political Action Committee

$25,250.00

Cash
$25,000.00
Paid by others
$250.00
Total
$25,250.00
fundraiser $250.00

Also funds 140 other sitting lawmakers.

Derived recipient stock · Jul 2, 2024 to Oct 24, 2026. State data as of Nov 4, 2026.

TEC account match.

Team
Sources

Derived itemized flow · Dec 4, 2024 to Oct 9, 2025. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 100986801, 101009904, 101031351.

×

The Peck Family Trust

$25,000.00

Cash
$25,000.00
Paid by others
$0.00
Total
$25,000.00

Also funds 1 other sitting lawmakers.

Derived recipient stock · Dec 14, 2024 to Sep 18, 2026. State data as of Nov 4, 2026.

Name match, not a verified identity: normalized filed name and state.

Sources

Derived itemized flow · on Dec 14, 2024. State data as of Nov 4, 2026.

Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.

Report IDs: 100986801.

Votes

No floor vote loaded for this bill.

Fiscal

No fiscal note in the loaded record.

How this was graded

Analysis of text version I by claude-opus-5-5, Oct 20, 2026, against the published rubric.

Sources

Texas Senate · Filed Mar 5, 2025

03/17/2025 S Referred to Business & Commerce

Texas Legislature Online · Introduced

Data snapshot Oct 26, 2026 at 4:20 AM CDT. Grades, charges, quotes and corrections follow the published record.

Senate committee · Business & Commerce · Final status: Died in committee

Companion

HB 3970 by Darby (identical)

Subjects

Utilities--Electric

ELECTRIC RELIABILITY COUNCIL OF TEXAS (ERCOT)

PUBLIC UTILITY COMMISSION

Text

The text as introduced · 541 words

2025S0155-1 02/28/25

By: Parker
S.B. No. 1942

A BILL TO BE ENTITLED

AN ACT

relating to electricity planning for large loads.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:

SECTION 1. Subchapter D, Chapter 39, Utilities Code, is

amended by adding Section 39.169 to read as follows:

Sec. 39.169. LARGE LOAD INTERCONNECTION; RELIABILITY

PROGRAM. (a) In this section, "behind-the-meter generation" means

a new generation facility on the retail customer's side of the

meter.

(b) The commission by rule shall require the independent

organization certified under Section 39.151 for the ERCOT power

region to develop and implement an interconnection program to

provide an expedited interconnection process for operators of large

loads who agree to cease consuming energy from the power grid

through deployment of their behind-the-meter generation when

directed to by the independent organization. The program must be

available only to large loads that are a facility at a single site

with an aggregate peak power demand that exceeds a demand threshold

established by the independent organization. The threshold must be

at least 75 megawatts unless the independent organization

determines that a lower threshold will better ensure reliability in

the ERCOT power region.

(c) The program must require the independent organization

certified under Section 39.151 for the ERCOT power region and the

relevant electric cooperative, municipally owned utility, or

transmission and distribution utility to give priority to a large

load in the interconnection queue participating in the program.

(d) The program must provide that:

(1) an interconnection application for a

participating large load with behind-the-meter generation that

agrees to offer the energy generated by the behind-the-meter

generation to the power grid at times directed by the independent

organization or reduce its energy consumption from the power grid

to a minimum level established by the independent organization will

be given priority over other interconnection applications that are

pending before the independent organization and the relevant

electric cooperative, municipally owned utility, or transmission

and distribution utility, including any applications from other

participating large loads without behind-the-meter generation;

(2) if applicable, the generator interconnection

application for a participating large load's behind-the-meter

generation will be processed in parallel with the load

interconnection application; and

(3) an applicant for participation in the program may

choose:

(A) if authorized by the independent

organization and the relevant electric cooperative, municipally

owned utility, or transmission and distribution utility, to

contract with a vendor approved by the relevant electric

cooperative, municipally owned utility, or transmission and

distribution utility or by the independent organization to perform

all studies required by the relevant electric cooperative,

municipally owned utility, or transmission and distribution

utility before the approval of the interconnection application;

(B) to procure equipment required for the

interconnection in accordance with technical specifications

provided by the relevant electric cooperative, municipally owned

utility, or transmission and distribution utility; and

(C) to construct interconnection facilities in

accordance with technical and other requirements of the relevant

electric cooperative, municipally owned utility, or transmission

and distribution utility.

(e) The program shall provide that studies required by an

electric cooperative, municipally owned utility, or transmission

and distribution utility before the approval of an interconnection

application for a participating large load may evaluate the load as

non-firm.

SECTION 2. This Act takes effect September 1, 2025.