Carve-out
One kind of generator, nuclear fission reactors, is excused from a cost rule that still binds every other power plant. The caption names nuclear, but the 'advanced' label is defined to cover large conventional-size reactors too.
Carve-outInitial review · graded Oct 20, 2026 · Headline, summary and grade are analysis of the bill text, not a finding about any person · How we grade
Caption
relating to a cost overage exemption for interconnection of advanced nuclear reactors to the ERCOT transmission system.
Caption from analyzed text · version I.
Summary
Interconnection costs over the allowance skip the reactor owner. Who pays instead? The bill doesn’t say.
Under current law, interconnection costs above the utility's allowance must be charged to the power plant that connects to the ERCOT grid. This bill exempts any fission nuclear reactor up to 1,400 megawatts, from microreactors to large plants, from paying those excess costs itself. The bill does not say who pays instead, so those overage costs are no longer charged directly to the nuclear plant owner, starting September 1, 2025.
Labels
Labels: NEVER GOT A HEARING. Filed Mar 11, 2025 and referred to the Senate Business & Commerce committee. No public hearing. The bill died.
Receipt
The receipt
89R-SB2315 · 2025-03-11
SOLD BY
ITEM
relating to a cost overage exemption for interconnection of advanced nuclear reactors to the ERCOT transmission system.
WHAT IT DOES
Interconnection costs over the allowance skip the reactor owner. Who pays instead? The bill doesn’t say.
Under current law, interconnection costs above the utility's allowance must be charged to the power plant that connects to the ERCOT grid. This bill exempts any fission nuclear reactor up to 1,400 megawatts, from microreactors to large plants, from paying those excess costs itself. The bill does not say who pays instead, so those overage costs are no longer charged directly to the nuclear plant owner, starting September 1, 2025.
CHARGES
[x] CARVE-OUTanalysis confidence 55%
One kind of generator, nuclear fission reactors, is excused from a cost rule that still binds every other power plant. The caption names nuclear, but the 'advanced' label is defined to cover large conventional-size reactors too.
TOTAL
No fiscal note in the loaded record.
HISTORY
- Received by the Secretary of the Senate
- Filed
- Read first time
- Referred to Business & Commerce
FILED UNDER
DATA CENTERS, WATER AND THE GRID
THE TEXT
…“generation resources with the ERCOT transmission system must be”…
Bill text, introduced version (I)
The bill changes who pays for connecting nuclear plants to the ERCOT grid and removes the requirement that the plant itself pay the overage.
THE TEXT
…“directly assigned to and collected from the generation resource”…
Bill text, introduced version (I)
Nuclear plant developers are relieved of interconnection costs that every other type of generator must still pay.
THANK YOU FOR CHECKING THE RECEIPT
CAMPAIGN PAID FOR BY
CAMPAIGN PAID FOR BY
Donors
Not tied to this bill.
Sources
The author's campaign account only. Own money and internal transfers are separate on the member page.
Derived itemized flow · Oct 28, 2024 to Jun 29, 2026. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Texas Stock Exchange | TXSE Group PAC$40,000.00
Texas Stock Exchange | TXSE Group PAC
$40,000.00
- Cash
- $40,000.00
- Paid by others
- $0.00
- Total
- $40,000.00
Also funds 10 other sitting lawmakers.
Derived recipient stock · Feb 17, 2026 to Oct 16, 2026. State data as of Nov 4, 2026.
TEC account match.
TeamSources
Derived itemized flow · Feb 17, 2026 to Jun 25, 2026. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 101060289.
Texas REALTORS Political Action Committee$25,250.00
Texas REALTORS Political Action Committee
$25,250.00
- Cash
- $25,000.00
- Paid by others
- $250.00
- Total
- $25,250.00
Also funds 140 other sitting lawmakers.
Derived recipient stock · Jul 2, 2024 to Oct 24, 2026. State data as of Nov 4, 2026.
TEC account match.
TeamSources
Derived itemized flow · Dec 4, 2024 to Oct 9, 2025. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 100986801, 101009904, 101031351.
The Peck Family Trust$25,000.00
The Peck Family Trust
$25,000.00
- Cash
- $25,000.00
- Paid by others
- $0.00
- Total
- $25,000.00
Also funds 1 other sitting lawmakers.
Derived recipient stock · Dec 14, 2024 to Sep 18, 2026. State data as of Nov 4, 2026.
Name match, not a verified identity: normalized filed name and state.
Sources
Derived itemized flow · on Dec 14, 2024. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 100986801.
Missing data does not establish zero giving. Display amounts are rounded.
Texas Stock Exchange | TXSE Group PAC
$40,000.00
- Cash
- $40,000.00
- Paid by others
- $0.00
- Total
- $40,000.00
Also funds 10 other sitting lawmakers.
Derived recipient stock · Feb 17, 2026 to Oct 16, 2026. State data as of Nov 4, 2026.
TEC account match.
TeamSources
Derived itemized flow · Feb 17, 2026 to Jun 25, 2026. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 101060289.
Texas REALTORS Political Action Committee
$25,250.00
- Cash
- $25,000.00
- Paid by others
- $250.00
- Total
- $25,250.00
Also funds 140 other sitting lawmakers.
Derived recipient stock · Jul 2, 2024 to Oct 24, 2026. State data as of Nov 4, 2026.
TEC account match.
TeamSources
Derived itemized flow · Dec 4, 2024 to Oct 9, 2025. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 100986801, 101009904, 101031351.
The Peck Family Trust
$25,000.00
- Cash
- $25,000.00
- Paid by others
- $0.00
- Total
- $25,000.00
Also funds 1 other sitting lawmakers.
Derived recipient stock · Dec 14, 2024 to Sep 18, 2026. State data as of Nov 4, 2026.
Name match, not a verified identity: normalized filed name and state.
Sources
Derived itemized flow · on Dec 14, 2024. State data as of Nov 4, 2026.
Derived itemized contributions on live regular reports and uncovered special-session dates. Internal account transfers and daily reports are excluded.
Report IDs: 100986801.
Votes
No floor vote loaded for this bill.
Fiscal
No fiscal note in the loaded record.
How this was graded
Analysis of text version I by claude-opus-5-5, Oct 20, 2026, against the published rubric.
Sources
Texas Senate · Filed Mar 11, 2025
03/25/2025 S Referred to Business & Commerce
Texas Legislature Online · Introduced
Data snapshot Oct 26, 2026 at 4:20 AM CDT. Grades, charges, quotes and corrections follow the published record.
Senate committee · Business & Commerce · Final status: Died in committee
Companion
HB 5590 by Harris (identical)
Subjects
Energy--Nuclear
ELECTRIC RELIABILITY COUNCIL OF TEXAS (ERCOT)
Text
The text as introduced · 187 words
89R9644 SCR-D By: Parker S.B. No. 2315 A BILL TO BE ENTITLED AN ACT relating to a cost overage exemption for interconnection of advanced nuclear reactors to the ERCOT transmission system. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: SECTION 1. Section 35.004(d-2), Utilities Code, is amended to read as follows: (d-2) Costs in excess of the transmission-owning utility allowance provided by Subsection (d-1) incurred to interconnect generation resources with the ERCOT transmission system must be directly assigned to and collected from the generation resource interconnecting through the facilities. This subsection does not apply to excess costs incurred to interconnect a generation resource that is an advanced nuclear reactor. For purposes of this subsection, an advanced nuclear reactor is a fission-based reactor belonging to one of the following categories: (1) a large reactor, with a generation capacity between 400 and 1400 megawatts of electricity; (2) a small modular reactor, with a generation capacity between 50 and 400 megawatts of electricity; or (3) a microreactor, with a generation capacity of less than 50 megawatts of electricity. SECTION 2. This Act takes effect September 1, 2025.